Construction of a Technical Salt Warehouse for 1rd Production Unit
The technical salt warehouse for 1 rd Production Unit was built in record time in 20 months. The unique method of mounting wooden glued arches with enlarged blocks allowed to reduce the construction time. The existing foundations were reinforced with a monolithic reinforced concrete hooping. The device of a suspended gallery with a width of 5m at the level of +16,800 is made. The roof coating is made of rolled materials on a double boardwalk.
The warehouse dimensions are 45 x 256m and height +23.15 m to the ridge hinge of the arch.